Clermont County, Ohio · 1.13MI.N.OF JCT.SR28 · Structure no. 1359118

Built
1990
35 years old
Condition
Good
inspected November 2023
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
30 ft
1 main span
Daily traffic
1,397
2015 count
Owner
County
County Highway Agency

About this bridge

Cook Road over Trib Horner Run is a prestressed concrete box beam or girders - multiple carrying Cook Road over Trib Horner Run in Clermont County, Ohio. It was built in 1990, so it is 35 years old, younger than the Ohio average of 47.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 1,397 vehicles a day, roughly 5% of them trucks, projected to reach 1,939 by 2035. The structure is 30 ft (9.1 m) long and 24 ft wide. If it were closed, the detour would be 6.2 mi (10 km).

CarriesCook Road
CrossesTrib Horner Run
Location1.13MI.N.OF JCT.SR28
RouteCounty Highway C0035
StateOhio
Coordinates39.20671, -84.24523
Functional classUrban Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Channel and channel protection8 Very GoodNo problems noted.
Last inspectionNovember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment9: Superior to present desirable criteria
Operating rating84.3 US tons
Inventory rating50.4 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans1
Design loadHS 20 + Mod
Structure length30 ft (9.1 m)
Longest span27 ft (8.2 m)
Deck width24 ft (7.3 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic1,397 (2015)
Projected traffic1,939 by 2035
Trucks5%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed6.2 mi (10 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Cook Road over Trib Horner Run built?

It was built in 1990, making it 35 years old in 2025.

What condition is Cook Road over Trib Horner Run in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2023.

How much traffic does Cook Road over Trib Horner Run carry?

About 1,397 vehicles per day (2015 count), of which roughly 5% are trucks.

How long is Cook Road over Trib Horner Run?

The structure is 30 ft (9.1 m) long with a longest span of 27 ft (8.2 m) and a deck 24 ft wide.

Who owns Cook Road over Trib Horner Run?

It is owned by the County Highway Agency.