Townline Lima Road over Pusheta Creek
GoodAuglaize County, Ohio · 0.1 MI N. of C.R. 100 · Structure no. 0635279
- Built
- 1959
- 66 years old, rebuilt 2018
- Condition
- Good
- inspected April 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 50 ft
- 1 main span
- Daily traffic
- 350
- 2018 count
- Owner
- County
- County Highway Agency
About this bridge
Townline Lima Road over Pusheta Creek is a steel stringer/multi-beam or girder carrying Townline Lima Road over Pusheta Creek in Auglaize County, Ohio. It was built in 1959 and reconstructed in 2018, so it is 66 years old, older than the Ohio average of 47.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 350 vehicles a day, roughly 3% of them trucks, projected to reach 420 by 2045. The structure is 50 ft (15.2 m) long and 24 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Townline Lima Road over Pusheta Creek built?
It was built in 1959, making it 66 years old in 2025. It was reconstructed in 2018.
What condition is Townline Lima Road over Pusheta Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2023.
How much traffic does Townline Lima Road over Pusheta Creek carry?
About 350 vehicles per day (2018 count), of which roughly 3% are trucks.
How long is Townline Lima Road over Pusheta Creek?
The structure is 50 ft (15.2 m) long with a longest span of 49 ft (15 m) and a deck 24 ft wide.
Who owns Townline Lima Road over Pusheta Creek?
It is owned by the County Highway Agency.