Central Parkway over 907K 907K87012001 RTE 9
FairWestchester County, New York · 0.6 MI E JCT Rts Ccp+brp · Structure no. 000000005501230
- Built
- 1964
- 61 years old
- Condition
- Fair
- inspected May 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 139 ft
- 2 main spans
- Daily traffic
- 1,702
- 2018 count
- Owner
- State
- State Highway Agency
About this bridge
Central Parkway over 907K 907K87012001 RTE 9 is a steel stringer/multi-beam or girder carrying Central Parkway over 907K 907K87012001 RTE 9 in Westchester County, New York. It was built in 1964, so it is 61 years old, older than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 1,702 vehicles a day, roughly 2% of them trucks, projected to reach 2,383 by 2038. The structure is 139 ft (42.4 m) long and 61 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Central Parkway over 907K 907K87012001 RTE 9 built?
It was built in 1964, making it 61 years old in 2025.
What condition is Central Parkway over 907K 907K87012001 RTE 9 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in May 2024.
How much traffic does Central Parkway over 907K 907K87012001 RTE 9 carry?
About 1,702 vehicles per day (2018 count), of which roughly 2% are trucks.
How long is Central Parkway over 907K 907K87012001 RTE 9?
The structure is 139 ft (42.4 m) long with a longest span of 67 ft (20.4 m) and a deck 61 ft wide.
Who owns Central Parkway over 907K 907K87012001 RTE 9?
It is owned by the State Highway Agency.