RTE I95 over Station Parking 120 Pur
GoodWestchester County, New York · 0.8 MI W JCT Rts I95+287 · Structure no. 000000005037319
- Built
- 1957
- 68 years old, rebuilt 1995
- Condition
- Good
- inspected August 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 445 ft
- 8 main spans
- Daily traffic
- 101,329
- 2018 count
- Owner
- Toll Authority
- State Toll Authority
About this bridge
RTE I95 over Station Parking 120 Pur is a steel stringer/multi-beam or girder carrying RTE I95 over Station Parking 120 Pur in Westchester County, New York. It was built in 1957 and reconstructed in 1995, so it is 68 years old, older than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 101,329 vehicles a day, roughly 14% of them trucks, projected to reach 171,590 by 2041. The structure is 445 ft (135.6 m) long and 117 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE I95 over Station Parking 120 Pur built?
It was built in 1957, making it 68 years old in 2025. It was reconstructed in 1995.
What condition is RTE I95 over Station Parking 120 Pur in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does RTE I95 over Station Parking 120 Pur carry?
About 101,329 vehicles per day (2018 count), of which roughly 14% are trucks.
How long is RTE I95 over Station Parking 120 Pur?
The structure is 445 ft (135.6 m) long with a longest span of 76 ft (23.2 m) and a deck 117 ft wide.
Who owns RTE I95 over Station Parking 120 Pur?
It is owned by the State Toll Authority.