RTE 20A over Honeoye Creek
GoodOntario County, New York · JCT RTE 20A +honeoye Outl · Structure no. 000000001016220
- Built
- 2011
- 14 years old
- Condition
- Good
- inspected October 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 75 ft
- 1 main span
- Daily traffic
- 5,578
- 2019 count
- Owner
- State
- State Highway Agency
About this bridge
RTE 20A over Honeoye Creek is a prestressed concrete box beam or girders - multiple carrying RTE 20A over Honeoye Creek in Ontario County, New York. It was built in 2011, so it is 14 years old, younger than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,578 vehicles a day, roughly 7% of them trucks, projected to reach 5,818 by 2041. The structure is 75 ft (22.9 m) long and 50 ft wide. If it were closed, the detour would be 24.9 mi (40 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE 20A over Honeoye Creek built?
It was built in 2011, making it 14 years old in 2025.
What condition is RTE 20A over Honeoye Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2023.
How much traffic does RTE 20A over Honeoye Creek carry?
About 5,578 vehicles per day (2019 count), of which roughly 7% are trucks.
How long is RTE 20A over Honeoye Creek?
The structure is 75 ft (22.9 m) long with a longest span of 72 ft (21.9 m) and a deck 50 ft wide.
Who owns RTE 20A over Honeoye Creek?
It is owned by the State Highway Agency.