RTE I278 over Hamilton to Carey Hamil
FairKings County, New York · Gowanus EB to Bqe EB · Structure no. 00000000106531O
- Built
- 1964
- 61 years old, rebuilt 2006
- Condition
- Fair
- inspected November 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 906 ft
- 17 main spans
- Daily traffic
- 161,771
- 2011 count
- Owner
- State
- State Highway Agency
About this bridge
RTE I278 over Hamilton to Carey Hamil is a steel stringer/multi-beam or girder carrying RTE I278 over Hamilton to Carey Hamil in Kings County, New York. It was built in 1964 and reconstructed in 2006, so it is 61 years old, older than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 161,771 vehicles a day, roughly 10% of them trucks, projected to reach 226,479 by 2031. The structure is 906 ft (276.1 m) long and 36 ft wide.
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE I278 over Hamilton to Carey Hamil built?
It was built in 1964, making it 61 years old in 2025. It was reconstructed in 2006.
What condition is RTE I278 over Hamilton to Carey Hamil in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in November 2024.
How much traffic does RTE I278 over Hamilton to Carey Hamil carry?
About 161,771 vehicles per day (2011 count), of which roughly 10% are trucks.
How long is RTE I278 over Hamilton to Carey Hamil?
The structure is 906 ft (276.1 m) long with a longest span of 75 ft (22.8 m) and a deck 36 ft wide.
Who owns RTE I278 over Hamilton to Carey Hamil?
It is owned by the State Highway Agency.