RTE I278 over Relief
FairKings County, New York · 2.3 MI SW JCT NY27 & I278 · Structure no. 00000000106531D
- Built
- 1963
- 62 years old, rebuilt 2010
- Condition
- Fair
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 435 ft
- 8 main spans
- Daily traffic
- 55,432
- 2018 count
- Owner
- State
- State Highway Agency
About this bridge
RTE I278 over Relief is a steel stringer/multi-beam or girder carrying RTE I278 over Relief in Kings County, New York. It was built in 1963 and reconstructed in 2010, so it is 62 years old, older than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 55,432 vehicles a day, roughly 2% of them trucks, projected to reach 68,347 by 2041. The structure is 435 ft (132.6 m) long and 25 ft wide.
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE I278 over Relief built?
It was built in 1963, making it 62 years old in 2025. It was reconstructed in 2010.
What condition is RTE I278 over Relief in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in August 2024.
How much traffic does RTE I278 over Relief carry?
About 55,432 vehicles per day (2018 count), of which roughly 2% are trucks.
How long is RTE I278 over Relief?
The structure is 435 ft (132.6 m) long with a longest span of 67 ft (20.4 m) and a deck 25 ft wide.
Who owns RTE I278 over Relief?
It is owned by the State Highway Agency.