GoodHerkimer County, New York · West Side Vllge of Poland · Structure no. 000000001051270
- Built
- 2016
- 9 years old
- Condition
- Good
- inspected July 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 252 ft
- 2 main spans
- Daily traffic
- 5,161
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
RTE 8 over West Canada Creek is a steel continuous stringer/multi-beam or girder carrying RTE 8 over West Canada Creek in Herkimer County, New York. It was built in 2016, so it is 9 years old, younger than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 5,161 vehicles a day, roughly 13% of them trucks, projected to reach 5,192 by 2041. The structure is 252 ft (76.8 m) long and 45 ft wide. If it were closed, the detour would be 30.4 mi (49 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 9 Excellent | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE 8 over West Canada Creek built?
It was built in 2016, making it 9 years old in 2025.
What condition is RTE 8 over West Canada Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.
How much traffic does RTE 8 over West Canada Creek carry?
About 5,161 vehicles per day (2020 count), of which roughly 13% are trucks.
How long is RTE 8 over West Canada Creek?
The structure is 252 ft (76.8 m) long with a longest span of 125 ft (38.1 m) and a deck 45 ft wide.
Who owns RTE 8 over West Canada Creek?
It is owned by the State Highway Agency.