RTE 219 over Norfolk Southern
FairErie County, New York · .6 MI S JCT US 219 & I90 · Structure no. 000000001062971
- Built
- 1972
- 53 years old, rebuilt 2009
- Condition
- Fair
- inspected October 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 401 ft
- 6 main spans
- Daily traffic
- 30,205
- 2020 count
- Owner
- State
- State Highway Agency
About this bridge
RTE 219 over Norfolk Southern is a steel stringer/multi-beam or girder carrying RTE 219 over Norfolk Southern in Erie County, New York. It was built in 1972 and reconstructed in 2009, so it is 53 years old, younger than the New York average of 53 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 30,205 vehicles a day, roughly 6% of them trucks, projected to reach 35,001 by 2041. The structure is 401 ft (122.2 m) long and 52 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was RTE 219 over Norfolk Southern built?
It was built in 1972, making it 53 years old in 2025. It was reconstructed in 2009.
What condition is RTE 219 over Norfolk Southern in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in October 2023.
How much traffic does RTE 219 over Norfolk Southern carry?
About 30,205 vehicles per day (2020 count), of which roughly 6% are trucks.
How long is RTE 219 over Norfolk Southern?
The structure is 401 ft (122.2 m) long with a longest span of 78 ft (23.7 m) and a deck 52 ft wide.
Who owns RTE 219 over Norfolk Southern?
It is owned by the State Highway Agency.