CR 653 (clove Rd) over Mill Brook Branch
GoodSussex County, New Jersey · 2.85 MI West of Rt Nj 23 · Structure no. 1900M16
- Built
- 2009
- 16 years old
- Condition
- Good
- inspected February 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 40 ft
- 1 main span
- Daily traffic
- 2,649
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
CR 653 (clove Rd) over Mill Brook Branch is a prestressed concrete box beam or girders - multiple carrying CR 653 (clove Rd) over Mill Brook Branch in Sussex County, New Jersey. It was built in 2009, so it is 16 years old, younger than the New Jersey average of 58.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 2,649 vehicles a day, roughly 3% of them trucks, projected to reach 3,179 by 2043. The structure is 40 ft (12.2 m) long and 36 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was CR 653 (clove Rd) over Mill Brook Branch built?
It was built in 2009, making it 16 years old in 2025.
What condition is CR 653 (clove Rd) over Mill Brook Branch in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.
How much traffic does CR 653 (clove Rd) over Mill Brook Branch carry?
About 2,649 vehicles per day (2023 count), of which roughly 3% are trucks.
How long is CR 653 (clove Rd) over Mill Brook Branch?
The structure is 40 ft (12.2 m) long with a longest span of 32 ft (9.8 m) and a deck 36 ft wide.
Who owns CR 653 (clove Rd) over Mill Brook Branch?
It is owned by the County Highway Agency.