Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP
GoodMonmouth County, New Jersey · 0.5 MI S. of Miller St. · Structure no. 1315169
- Built
- 2009
- 16 years old
- Condition
- Good
- inspected March 2023
- Type
- Segmental Box Girder
- Prestressed Concrete Continuous
- Length
- 1,611 ft
- 9 main spans
- Daily traffic
- 14,038
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP is a prestressed concrete continuous segmental box girder carrying Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP in Monmouth County, New Jersey. It was built in 2009, so it is 16 years old, younger than the New Jersey average of 58.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 14,038 vehicles a day, roughly 4% of them trucks, projected to reach 16,845 by 2043. The structure is 1,611 ft (491 m) long and 92 ft wide. If it were closed, the detour would be 9.9 mi (16 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 9 Excellent | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP built?
It was built in 2009, making it 16 years old in 2025.
What condition is Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in March 2023.
How much traffic does Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP carry?
About 14,038 vehicles per day (2023 count), of which roughly 4% are trucks.
How long is Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP?
The structure is 1,611 ft (491 m) long with a longest span of 232 ft (70.7 m) and a deck 92 ft wide.
Who owns Nj 36 (ocean Ave) over Shrewsbury RIV/CR8/RAMP?
It is owned by the State Highway Agency.