US Bridges

Main Street over Deal Lake

Good

Monmouth County, New Jersey · 0.3MI. So. of Corlies Ave · Structure no. 1300O11

Built
2017
8 years old
Condition
Good
inspected May 2023
Type
Slab
Prestressed Concrete
Length
43 ft
1 main span
Daily traffic
6,351
2023 count
Owner
County
County Highway Agency

About this bridge

Main Street over Deal Lake is a prestressed concrete slab carrying Main Street over Deal Lake in Monmouth County, New Jersey. It was built in 2017, so it is 8 years old, younger than the New Jersey average of 58.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 6,351 vehicles a day, roughly 3% of them trucks, projected to reach 7,621 by 2043. The structure is 43 ft (13.1 m) long and 53 ft wide. If it were closed, the detour would be 1.2 mi (2 km).

CarriesMain Street
CrossesDeal Lake
Location0.3MI. So. of Corlies Ave
RouteCity Street 0
Coordinates40.23232, -74.00781
Functional classUrban Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionMay 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry3: Basically intolerable, requiring high priority of corrective action
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating106.8 US tons
Inventory rating74 US tons

Structure

Structure typeSlab
MaterialPrestressed Concrete
DeckConcrete, cast-in-place
Main spans1
Design loadHL 93
Structure length43 ft (13.1 m)
Longest span41 ft (12.5 m)
Deck width53 ft (16.1 m)
Roadway width30 ft (9.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic6,351 (2023)
Projected traffic7,621 by 2043
Trucks3%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesWaterway
Detour if closed1.2 mi (2 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Main Street over Deal Lake built?

It was built in 2017, making it 8 years old in 2025.

What condition is Main Street over Deal Lake in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2023.

How much traffic does Main Street over Deal Lake carry?

About 6,351 vehicles per day (2023 count), of which roughly 3% are trucks.

How long is Main Street over Deal Lake?

The structure is 43 ft (13.1 m) long with a longest span of 41 ft (12.5 m) and a deck 53 ft wide.

Who owns Main Street over Deal Lake?

It is owned by the County Highway Agency.