Lakeside Drive over Crystal Lake Spillway
GoodBergen County, New Jersey · 400 Ft. West of CR 507 · Structure no. 020027M
- Built
- 1912
- 113 years old, rebuilt 2009
- Condition
- Good
- inspected May 2024
- Type
- Slab
- Prestressed Concrete
- Length
- 39 ft
- 1 main span
- Daily traffic
- 607
- 2024 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
Lakeside Drive over Crystal Lake Spillway is a prestressed concrete slab carrying Lakeside Drive over Crystal Lake Spillway in Bergen County, New Jersey. It was built in 1912 and reconstructed in 2009, so it is 113 years old, older than the New Jersey average of 58.5 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 607 vehicles a day, roughly 1% of them trucks, projected to reach 741 by 2044. The structure is 39 ft (11.9 m) long and 20 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Lakeside Drive over Crystal Lake Spillway built?
It was built in 1912, making it 113 years old in 2025. It was reconstructed in 2009.
What condition is Lakeside Drive over Crystal Lake Spillway in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in May 2024.
How much traffic does Lakeside Drive over Crystal Lake Spillway carry?
About 607 vehicles per day (2024 count), of which roughly 1% are trucks.
How long is Lakeside Drive over Crystal Lake Spillway?
The structure is 39 ft (11.9 m) long with a longest span of 34 ft (10.4 m) and a deck 20 ft wide.
Who owns Lakeside Drive over Crystal Lake Spillway?
It is owned by the Town or Township Highway Agency.