US Bridges

Main Street over Merrimack River CSX RD

Good

Merrimack County, New Hampshire · 0.7 MI N JCT US 3 · Structure no. 012800800014800

Built
1976
49 years old
Condition
Good
inspected June 2024
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
675 ft
5 main spans
Daily traffic
15,760
2023 count
Owner
State
State Highway Agency

About this bridge

Main Street over Merrimack River CSX RD is a steel continuous stringer/multi-beam or girder carrying Main Street over Merrimack River CSX RD in Merrimack County, New Hampshire. It was built in 1976, so it is 49 years old, younger than the New Hampshire average of 56.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 15,760 vehicles a day, roughly 4% of them trucks, projected to reach 23,324 by 2043. The structure is 675 ft (205.7 m) long and 42 ft wide. If it were closed, the detour would be 11.8 mi (19 km).

CarriesMain Street
CrossesMerrimack River CSX RD
Location0.7 MI N JCT US 3
RouteCity Street 0
Coordinates43.09542, -71.46444
Functional classUrban Other Principal Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection7 GoodSome minor problems.
Last inspectionJune 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation7: Better than present minimum criteria
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating46.2 US tons
Inventory rating35.7 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans5
Design loadHS 20 + Mod
Structure length675 ft (205.7 m)
Longest span175 ft (53.3 m)
Deck width42 ft (12.8 m)
Roadway width34 ft (10.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic15,760 (2023)
Projected traffic23,324 by 2043
Trucks4%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesHighway, waterway and railroad
Detour if closed11.8 mi (19 km)
TollOn a free road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusPossibly eligible for the National Register; requires further investigation
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$314,000 (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was Main Street over Merrimack River CSX RD built?

It was built in 1976, making it 49 years old in 2025.

What condition is Main Street over Merrimack River CSX RD in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.

How much traffic does Main Street over Merrimack River CSX RD carry?

About 15,760 vehicles per day (2023 count), of which roughly 4% are trucks.

How long is Main Street over Merrimack River CSX RD?

The structure is 675 ft (205.7 m) long with a longest span of 175 ft (53.3 m) and a deck 42 ft wide.

Who owns Main Street over Merrimack River CSX RD?

It is owned by the State Highway Agency.