Transfer Station R over Orange Brook

Fair

Grafton County, New Hampshire · 0.4 MI South Orange RD · Structure no. 003601910008000

Built
1980
45 years old
Condition
Fair
inspected September 2024
Type
Slab
Concrete
Length
40 ft
4 main spans
Daily traffic
96
2023 count
Owner
City
City or Municipal Highway Agency

About this bridge

Transfer Station R over Orange Brook is a concrete slab carrying Transfer Station R over Orange Brook in Grafton County, New Hampshire. It was built in 1980, so it is 45 years old, younger than the New Hampshire average of 56.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

It carries about 96 vehicles a day, roughly 8% of them trucks, projected to reach 142 by 2043. The structure is 40 ft (12.2 m) long and 16 ft wide. If it were closed, the detour would be 123.7 mi (199 km).

CarriesTransfer Station R
CrossesOrange Brook
Location0.4 MI South Orange RD
RouteCity Street 0
Coordinates43.64813, -71.99945
Functional classRural Local

Condition and inspection

Fair

The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.

ComponentRatingMeaning
Deck5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Superstructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Substructure5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionSeptember 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation5: Somewhat better than minimum adequacy to tolerate being left in place as is
Deck geometry3: Basically intolerable, requiring high priority of corrective action
Waterway adequacy5: Somewhat better than minimum adequacy to tolerate being left in place as is
Approach roadway alignment6: Equal to present minimum criteria
Operating rating60 US tons
Inventory rating36 US tons

Structure

Structure typeSlab
MaterialConcrete
DeckConcrete, precast panels
Main spans4
Design loadUnknown
Structure length40 ft (12.2 m)
Longest span10 ft (3 m)
Deck width16 ft (4.9 m)
Roadway width16 ft (4.9 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic96 (2023)
Projected traffic142 by 2043
Trucks8%
Lanes on structure1
Traffic directionOne-way traffic
CarriesHighway
CrossesWaterway
Detour if closed123.7 mi (199 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCity or Municipal Highway Agency
Maintained byCity or Municipal Highway Agency
Historic statusPossibly eligible for the National Register; requires further investigation
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$314,000 (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was Transfer Station R over Orange Brook built?

It was built in 1980, making it 45 years old in 2025.

What condition is Transfer Station R over Orange Brook in?

The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in September 2024.

How much traffic does Transfer Station R over Orange Brook carry?

About 96 vehicles per day (2023 count), of which roughly 8% are trucks.

How long is Transfer Station R over Orange Brook?

The structure is 40 ft (12.2 m) long with a longest span of 10 ft (3 m) and a deck 16 ft wide.

Who owns Transfer Station R over Orange Brook?

It is owned by the City or Municipal Highway Agency.