FairPosted for loadBottineau County, North Dakota · 8 North 2 West of Kramer · Structure no. 000000005134140
- Built
- 1969
- 56 years old
- Condition
- Fair
- inspected August 2023
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 46 ft
- 1 main span
- Daily traffic
- 5
- 2018 count
- Owner
- County
- County Highway Agency
About this bridge
Section Line Trail over Boundary Creek is a prestressed concrete box beam or girders - multiple carrying Section Line Trail over Boundary Creek in Bottineau County, North Dakota. It was built in 1969, so it is 56 years old, older than the North Dakota average of 48.2 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 5 vehicles a day, projected to reach 5 by 2038. The structure is 46 ft (14 m) long and 25 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Section Line Trail over Boundary Creek built?
It was built in 1969, making it 56 years old in 2025.
What condition is Section Line Trail over Boundary Creek in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in August 2023.
How much traffic does Section Line Trail over Boundary Creek carry?
About 5 vehicles per day (2018 count).
How long is Section Line Trail over Boundary Creek?
The structure is 46 ft (14 m) long with a longest span of 43 ft (13.1 m) and a deck 25 ft wide.
Who owns Section Line Trail over Boundary Creek?
It is owned by the County Highway Agency.