Nye Rd-S 419 over W Rosebud Creek Overflow
GoodStillwater County, Montana · Fishtail · Structure no. S00419003+05001
- Built
- 1991
- 34 years old
- Condition
- Good
- inspected January 2024
- Type
- Slab
- Concrete Continuous
- Length
- 40 ft
- 3 main spans
- Daily traffic
- 1,074
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
Nye Rd-S 419 over W Rosebud Creek Overflow is a concrete continuous slab carrying Nye Rd-S 419 over W Rosebud Creek Overflow in Stillwater County, Montana. It was built in 1991, so it is 34 years old, younger than the Montana average of 47 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 1,074 vehicles a day, roughly 4% of them trucks, projected to reach 1,128 by 2043. The structure is 40 ft (12.2 m) long and 38 ft wide. If it were closed, the detour would be 44.7 mi (72 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Nye Rd-S 419 over W Rosebud Creek Overflow built?
It was built in 1991, making it 34 years old in 2025.
What condition is Nye Rd-S 419 over W Rosebud Creek Overflow in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2024.
How much traffic does Nye Rd-S 419 over W Rosebud Creek Overflow carry?
About 1,074 vehicles per day (2023 count), of which roughly 4% are trucks.
How long is Nye Rd-S 419 over W Rosebud Creek Overflow?
The structure is 40 ft (12.2 m) long with a longest span of 27 ft (8.2 m) and a deck 38 ft wide.
Who owns Nye Rd-S 419 over W Rosebud Creek Overflow?
It is owned by the State Highway Agency.