US Bridges

Violet Road over ST Bayou Canal

Good

Humphreys County, Mississippi · Sec 18 T13N R 4W · Structure no. SA270000000A015

Built
2018
7 years old
Condition
Good
inspected December 2023
Type
Channel Beam
Concrete
Length
93 ft
3 main spans
Daily traffic
40
2018 count
Owner
County
County Highway Agency

About this bridge

Violet Road over ST Bayou Canal is a concrete channel beam carrying Violet Road over ST Bayou Canal in Humphreys County, Mississippi. It was built in 2018, so it is 7 years old, younger than the Mississippi average of 38.9 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 40 vehicles a day, projected to reach 60 by 2038. The structure is 93 ft (28.3 m) long and 32 ft wide. If it were closed, the detour would be 8.1 mi (13 km).

CarriesViolet Road
CrossesST Bayou Canal
LocationSec 18 T13N R 4W
RouteCounty Highway 216
Coordinates32.97469, -90.65656
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Channel and channel protection7 GoodSome minor problems.
Last inspectionDecember 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation8: Equal to present desirable criteria
Deck geometry7: Better than present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating48.2 US tons
Inventory rating37.1 US tons

Structure

Structure typeChannel Beam
MaterialConcrete
DeckConcrete, precast panels
Main spans3
Design loadHL 93
Structure length93 ft (28.3 m)
Longest span31 ft (9.4 m)
Deck width32 ft (9.9 m)
Roadway width30 ft (9.1 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic40 (2018)
Projected traffic60 by 2038
Trucks—
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed8.1 mi (13 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Violet Road over ST Bayou Canal built?

It was built in 2018, making it 7 years old in 2025.

What condition is Violet Road over ST Bayou Canal in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2023.

How much traffic does Violet Road over ST Bayou Canal carry?

About 40 vehicles per day (2018 count).

How long is Violet Road over ST Bayou Canal?

The structure is 93 ft (28.3 m) long with a longest span of 31 ft (9.4 m) and a deck 32 ft wide.

Who owns Violet Road over ST Bayou Canal?

It is owned by the County Highway Agency.