US Bridges

Mo 2 E over Mid Tebo CR

Good

Henry County, Missouri · S 5 T 43 N R 24 W · Structure no. 33596

Built
2011
14 years old
Condition
Good
inspected September 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
80 ft
1 main span
Daily traffic
849
2024 count
Owner
State
State Highway Agency

About this bridge

Mo 2 E over Mid Tebo CR is a prestressed concrete box beam or girders - multiple carrying Mo 2 E over Mid Tebo CR in Henry County, Missouri. It was built in 2011, so it is 14 years old, younger than the Missouri average of 45.1 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 849 vehicles a day, roughly 11% of them trucks, projected to reach 1,274 by 2044. The structure is 80 ft (24.4 m) long and 26 ft wide. If it were closed, the detour would be 18 mi (29 km).

CarriesMo 2 E
CrossesMid Tebo CR
LocationS 5 T 43 N R 24 W
RouteState Highway 2
Coordinates38.54405, -93.60222
Functional classRural Major Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure9 ExcellentNo problems noted.
Channel and channel protection7 GoodSome minor problems.
Last inspectionSeptember 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating76.4 US tons
Inventory rating43.7 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans1
Design loadHS 20
Structure length80 ft (24.4 m)
Longest span80 ft (24.4 m)
Deck width26 ft (7.9 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic849 (2024)
Projected traffic1,274 by 2044
Trucks11%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed18 mi (29 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Mo 2 E over Mid Tebo CR built?

It was built in 2011, making it 14 years old in 2025.

What condition is Mo 2 E over Mid Tebo CR in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2024.

How much traffic does Mo 2 E over Mid Tebo CR carry?

About 849 vehicles per day (2024 count), of which roughly 11% are trucks.

How long is Mo 2 E over Mid Tebo CR?

The structure is 80 ft (24.4 m) long with a longest span of 80 ft (24.4 m) and a deck 26 ft wide.

Who owns Mo 2 E over Mid Tebo CR?

It is owned by the State Highway Agency.