Airport RD over Camp CR
FairPosted for loadCass County, Missouri · S 28 T 45 N R 30 W · Structure no. 23165
- Built
- 1900
- 125 years old
- Condition
- Fair
- inspected April 2023
- Type
- Truss - Thru
- Steel
- Length
- 49 ft
- 1 main span
- Daily traffic
- 45
- 2024 count
- Owner
- County
- County Highway Agency
About this bridge
Airport RD over Camp CR is a steel truss - thru carrying Airport RD over Camp CR in Cass County, Missouri. It was built in 1900, so it is 125 years old, older than the Missouri average of 45.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 45 vehicles a day, roughly 5% of them trucks, projected to reach 72 by 2044. The structure is 49 ft (14.9 m) long and 14 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Airport RD over Camp CR built?
It was built in 1900, making it 125 years old in 2025.
What condition is Airport RD over Camp CR in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2023.
How much traffic does Airport RD over Camp CR carry?
About 45 vehicles per day (2024 count), of which roughly 5% are trucks.
How long is Airport RD over Camp CR?
The structure is 49 ft (14.9 m) long with a longest span of 47 ft (14.3 m) and a deck 14 ft wide.
Who owns Airport RD over Camp CR?
It is owned by the County Highway Agency.