Mo 142 E over Main Drain Dtch
GoodButler County, Missouri · S 8 T 22 N R 6 E · Structure no. 34126
- Built
- 2012
- 13 years old
- Condition
- Good
- inspected February 2025
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 112 ft
- 2 main spans
- Daily traffic
- 407
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
Mo 142 E over Main Drain Dtch is a prestressed concrete box beam or girders - multiple carrying Mo 142 E over Main Drain Dtch in Butler County, Missouri. It was built in 2012, so it is 13 years old, younger than the Missouri average of 45.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 407 vehicles a day, roughly 12% of them trucks, projected to reach 651 by 2044. The structure is 112 ft (34.2 m) long and 26 ft wide. If it were closed, the detour would be 14.3 mi (23 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 9 Excellent | No problems noted. |
| Superstructure | 9 Excellent | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Mo 142 E over Main Drain Dtch built?
It was built in 2012, making it 13 years old in 2025.
What condition is Mo 142 E over Main Drain Dtch in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2025.
How much traffic does Mo 142 E over Main Drain Dtch carry?
About 407 vehicles per day (2024 count), of which roughly 12% are trucks.
How long is Mo 142 E over Main Drain Dtch?
The structure is 112 ft (34.2 m) long with a longest span of 60 ft (18.3 m) and a deck 26 ft wide.
Who owns Mo 142 E over Main Drain Dtch?
It is owned by the State Highway Agency.