S.E. Mt Moriah over Malden CR
GoodBuchanan County, Missouri · S 30 T 56 N R 33 W · Structure no. 16353
- Built
- 1992
- 33 years old
- Condition
- Good
- inspected January 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 75 ft
- 1 main span
- Daily traffic
- 30
- 2024 count
- Owner
- County
- County Highway Agency
About this bridge
S.E. Mt Moriah over Malden CR is a steel stringer/multi-beam or girder carrying S.E. Mt Moriah over Malden CR in Buchanan County, Missouri. It was built in 1992, so it is 33 years old, younger than the Missouri average of 45.1 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 30 vehicles a day, roughly 10% of them trucks, projected to reach 35 by 2044. The structure is 75 ft (22.9 m) long and 25 ft wide. If it were closed, the detour would be 6.8 mi (11 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S.E. Mt Moriah over Malden CR built?
It was built in 1992, making it 33 years old in 2025.
What condition is S.E. Mt Moriah over Malden CR in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in January 2023.
How much traffic does S.E. Mt Moriah over Malden CR carry?
About 30 vehicles per day (2024 count), of which roughly 10% are trucks.
How long is S.E. Mt Moriah over Malden CR?
The structure is 75 ft (22.9 m) long with a longest span of 74 ft (22.6 m) and a deck 25 ft wide.
Who owns S.E. Mt Moriah over Malden CR?
It is owned by the County Highway Agency.