Houston County, Minnesota · 0.6 MI W of JCT Csah 6 · Structure no. 28522

Built
2000
25 years old
Condition
Good
inspected October 2024
Type
Slab
Concrete Continuous
Length
116 ft
3 main spans
Daily traffic
522
2021 count
Owner
County
County Highway Agency

About this bridge

Csah 25 over Pine Creek is a concrete continuous slab carrying Csah 25 over Pine Creek in Houston County, Minnesota. It was built in 2000, so it is 25 years old, younger than the Minnesota average of 38.5 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 522 vehicles a day, roughly 2% of them trucks, projected to reach 660 by 2041. The structure is 116 ft (35.5 m) long and 47 ft wide. If it were closed, the detour would be 6.8 mi (11 km).

CarriesCsah 25
CrossesPine Creek
Location0.6 MI W of JCT Csah 6
RouteCounty Highway 25
Coordinates43.81817, -91.32689
Functional classRural Minor Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionOctober 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour within limits of footing or piles
Structural evaluation7: Better than present minimum criteria
Deck geometry9: Superior to present desirable criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating87.1 US tons
Inventory rating52.1 US tons

Structure

Structure typeSlab
MaterialConcrete Continuous
DeckNot applicable
Main spans3
Design loadHS 25 or greater
Structure length116 ft (35.5 m)
Longest span44 ft (13.4 m)
Deck width47 ft (14.4 m)
Roadway width44 ft (13.4 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic522 (2021)
Projected traffic660 by 2041
Trucks2%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed6.8 mi (11 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Csah 25 over Pine Creek built?

It was built in 2000, making it 25 years old in 2025.

What condition is Csah 25 over Pine Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2024.

How much traffic does Csah 25 over Pine Creek carry?

About 522 vehicles per day (2021 count), of which roughly 2% are trucks.

How long is Csah 25 over Pine Creek?

The structure is 116 ft (35.5 m) long with a longest span of 44 ft (13.4 m) and a deck 47 ft wide.

Who owns Csah 25 over Pine Creek?

It is owned by the County Highway Agency.