Deer Path Trail over Paint Creek Drain
GoodOakland County, Michigan · In Subdivision Sec 33 · Structure no. 000000000013598
- Built
- 1999
- 26 years old
- Condition
- Good
- inspected July 2024
- Type
- Culvert
- Concrete
- Length
- 22 ft
- 1 main span
- Daily traffic
- 500
- 2010 count
- Owner
- County
- County Highway Agency
About this bridge
Deer Path Trail over Paint Creek Drain is a concrete culvert carrying Deer Path Trail over Paint Creek Drain in Oakland County, Michigan. It was built in 1999, so it is 26 years old, younger than the Michigan average of 48.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 500 vehicles a day, projected to reach 545 by 2030. The structure is 22 ft (6.7 m) long. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
| Culvert | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Deer Path Trail over Paint Creek Drain built?
It was built in 1999, making it 26 years old in 2025.
What condition is Deer Path Trail over Paint Creek Drain in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.
How much traffic does Deer Path Trail over Paint Creek Drain carry?
About 500 vehicles per day (2010 count).
How long is Deer Path Trail over Paint Creek Drain?
The structure is 22 ft (6.7 m) long with a longest span of 22 ft (6.7 m).
Who owns Deer Path Trail over Paint Creek Drain?
It is owned by the County Highway Agency.