I-196 WB Off Ramp over Danly Machine Bldg
FairKent County, Michigan · In Grand Rapids · Structure no. 000000000004798
- Built
- 1964
- 61 years old, rebuilt 2004
- Condition
- Fair
- inspected September 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 113 ft
- 2 main spans
- Daily traffic
- 5,800
- 1999 count
- Owner
- State
- State Highway Agency
About this bridge
I-196 WB Off Ramp over Danly Machine Bldg is a steel stringer/multi-beam or girder carrying I-196 WB Off Ramp over Danly Machine Bldg in Kent County, Michigan. It was built in 1964 and reconstructed in 2004, so it is 61 years old, older than the Michigan average of 48.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 5,800 vehicles a day, roughly 8% of them trucks, projected to reach 6,670 by 2019. The structure is 113 ft (34.4 m) long and 30 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I-196 WB Off Ramp over Danly Machine Bldg built?
It was built in 1964, making it 61 years old in 2025. It was reconstructed in 2004.
What condition is I-196 WB Off Ramp over Danly Machine Bldg in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in September 2023.
How much traffic does I-196 WB Off Ramp over Danly Machine Bldg carry?
About 5,800 vehicles per day (1999 count), of which roughly 8% are trucks.
How long is I-196 WB Off Ramp over Danly Machine Bldg?
The structure is 113 ft (34.4 m) long with a longest span of 70 ft (21.3 m) and a deck 30 ft wide.
Who owns I-196 WB Off Ramp over Danly Machine Bldg?
It is owned by the State Highway Agency.