Hemphill RD over I-475
PoorGenesee County, Michigan · @ S Flint City Lts · Structure no. 000000000002652
- Built
- 1971
- 54 years old
- Condition
- Poor
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 140 ft
- 2 main spans
- Daily traffic
- 15,000
- 1988 count
- Owner
- State
- State Highway Agency
About this bridge
Hemphill RD over I-475 is a steel continuous stringer/multi-beam or girder carrying Hemphill RD over I-475 in Genesee County, Michigan. It was built in 1971, so it is 54 years old, older than the Michigan average of 48.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 15,000 vehicles a day, roughly 3% of them trucks, projected to reach 17,250 by 2008. The structure is 140 ft (42.6 m) long and 66 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Hemphill RD over I-475 built?
It was built in 1971, making it 54 years old in 2025.
What condition is Hemphill RD over I-475 in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in April 2024.
How much traffic does Hemphill RD over I-475 carry?
About 15,000 vehicles per day (1988 count), of which roughly 3% are trucks.
How long is Hemphill RD over I-475?
The structure is 140 ft (42.6 m) long with a longest span of 70 ft (21.3 m) and a deck 66 ft wide.
Who owns Hemphill RD over I-475?
It is owned by the State Highway Agency.