M-13|N Huron RD over Pinconning River
GoodBay County, Michigan · In Pinconning · Structure no. 000000000000592
- Built
- 2009
- 16 years old
- Condition
- Good
- inspected April 2024
- Type
- Box Beam or Girders - Single or Spread
- Prestressed Concrete
- Length
- 49 ft
- 1 main span
- Daily traffic
- 9,924
- 2007 count
- Owner
- State
- State Highway Agency
About this bridge
M-13|N Huron RD over Pinconning River is a prestressed concrete box beam or girders - single or spread carrying M-13|N Huron RD over Pinconning River in Bay County, Michigan. It was built in 2009, so it is 16 years old, younger than the Michigan average of 48.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 9,924 vehicles a day, roughly 6% of them trucks, projected to reach 12,500 by 2030. The structure is 49 ft (14.9 m) long and 63 ft wide. If it were closed, the detour would be 3.1 mi (5 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was M-13|N Huron RD over Pinconning River built?
It was built in 2009, making it 16 years old in 2025.
What condition is M-13|N Huron RD over Pinconning River in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does M-13|N Huron RD over Pinconning River carry?
About 9,924 vehicles per day (2007 count), of which roughly 6% are trucks.
How long is M-13|N Huron RD over Pinconning River?
The structure is 49 ft (14.9 m) long with a longest span of 47 ft (14.4 m) and a deck 63 ft wide.
Who owns M-13|N Huron RD over Pinconning River?
It is owned by the State Highway Agency.