N Main ST over Schoodic
GoodWashington County, Maine · .4 MI S Townline · Structure no. 3649
- Built
- 2021
- 4 years old
- Condition
- Good
- inspected June 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 62 ft
- 1 main span
- Daily traffic
- 705
- 2016 count
- Owner
- State
- State Highway Agency
About this bridge
N Main ST over Schoodic is a prestressed concrete box beam or girders - multiple carrying N Main ST over Schoodic in Washington County, Maine. It was built in 2021, so it is 4 years old, younger than the Maine average of 53.7 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 705 vehicles a day, roughly 5% of them trucks, projected to reach 1,128 by 2036. The structure is 62 ft (18.9 m) long and 31 ft wide. If it were closed, the detour would be 51 mi (82 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was N Main ST over Schoodic built?
It was built in 2021, making it 4 years old in 2025.
What condition is N Main ST over Schoodic in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2024.
How much traffic does N Main ST over Schoodic carry?
About 705 vehicles per day (2016 count), of which roughly 5% are trucks.
How long is N Main ST over Schoodic?
The structure is 62 ft (18.9 m) long with a longest span of 60 ft (18.3 m) and a deck 31 ft wide.
Who owns N Main ST over Schoodic?
It is owned by the State Highway Agency.