US Bridges

Fuller RD over Harvey Brook

PoorPosted for load

Penobscot County, Maine · 0.9 MI E of JCT Five RD · Structure no. 5505

Built
1963
62 years old
Condition
Poor
inspected October 2024
Type
Tee Beam
Concrete
Length
29 ft
1 main span
Daily traffic
600
2016 count
Owner
State
State Highway Agency

About this bridge

Fuller RD over Harvey Brook is a concrete tee beam carrying Fuller RD over Harvey Brook in Penobscot County, Maine. It was built in 1963, so it is 62 years old, older than the Maine average of 53.7 years.

The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: posted for load restriction.

It carries about 600 vehicles a day, roughly 5% of them trucks, projected to reach 960 by 2036. The structure is 29 ft (8.8 m) long and 24 ft wide. If it were closed, the detour would be 3.1 mi (5 km).

CarriesFuller RD
CrossesHarvey Brook
Location0.9 MI E of JCT Five RD
RouteCity Street 0
StateMaine
Coordinates44.82107, -69.03974
Functional classRural Local

Condition and inspection

Poor

The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.

ComponentRatingMeaning
Deck4 PoorAdvanced section loss, deterioration, spalling or scour.
Superstructure4 PoorAdvanced section loss, deterioration, spalling or scour.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection5 FairAll primary structural elements are sound but may have minor section loss, cracking, spalling or scour.
Last inspectionOctober 2024
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourFoundations stable; action required to protect exposed foundations
Structural evaluation4: Meets minimum tolerable limits to be left in place as is
Deck geometry2: Basically intolerable, requiring high priority of replacement
Waterway adequacy9: Superior to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating19.8 US tons
Inventory rating19.8 US tons

Structure

Structure typeTee Beam
MaterialConcrete
DeckConcrete, precast panels
Main spans1
Design loadUnknown
Structure length29 ft (8.8 m)
Longest span21 ft (6.4 m)
Deck width24 ft (7.3 m)
Roadway width19 ft (5.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic600 (2016)
Projected traffic960 by 2036
Trucks5%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.1 mi (5 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Fuller RD over Harvey Brook built?

It was built in 1963, making it 62 years old in 2025.

What condition is Fuller RD over Harvey Brook in?

The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in October 2024.

How much traffic does Fuller RD over Harvey Brook carry?

About 600 vehicles per day (2016 count), of which roughly 5% are trucks.

How long is Fuller RD over Harvey Brook?

The structure is 29 ft (8.8 m) long with a longest span of 21 ft (6.4 m) and a deck 24 ft wide.

Who owns Fuller RD over Harvey Brook?

It is owned by the State Highway Agency.