Main ST W over Billy Brook
PoorOxford County, Maine · 0.9 MI Wly JCT RTE 160 · Structure no. 2821
- Built
- 1952
- 73 years old
- Condition
- Poor
- inspected July 2024
- Type
- Slab
- Concrete
- Length
- 24 ft
- 1 main span
- Daily traffic
- 1,195
- 2016 count
- Owner
- State
- State Highway Agency
About this bridge
Main ST W over Billy Brook is a concrete slab carrying Main ST W over Billy Brook in Oxford County, Maine. It was built in 1952, so it is 73 years old, older than the Maine average of 53.7 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 1,195 vehicles a day, roughly 5% of them trucks, projected to reach 1,793 by 2036. The structure is 24 ft (7.4 m) long and 31 ft wide. If it were closed, the detour would be 100 mi (161 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Main ST W over Billy Brook built?
It was built in 1952, making it 73 years old in 2025.
What condition is Main ST W over Billy Brook in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in July 2024.
How much traffic does Main ST W over Billy Brook carry?
About 1,195 vehicles per day (2016 count), of which roughly 5% are trucks.
How long is Main ST W over Billy Brook?
The structure is 24 ft (7.4 m) long with a longest span of 20 ft (6.1 m) and a deck 31 ft wide.
Who owns Main ST W over Billy Brook?
It is owned by the State Highway Agency.