Boundary Line Rd. over Whitney Brook
PoorAroostook County, Maine · 3 MI E JCT 1 · Structure no. 5012
- Built
- 1929
- 96 years old
- Condition
- Poor
- inspected June 2024
- Type
- Slab
- Concrete
- Length
- 24 ft
- 1 main span
- Daily traffic
- 153
- 2016 count
- Owner
- State
- State Highway Agency
About this bridge
Boundary Line Rd. over Whitney Brook is a concrete slab carrying Boundary Line Rd. over Whitney Brook in Aroostook County, Maine. It was built in 1929, so it is 96 years old, older than the Maine average of 53.7 years.
The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 4 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
It carries about 153 vehicles a day, roughly 5% of them trucks, projected to reach 245 by 2036. The structure is 24 ft (7.3 m) long and 27 ft wide. If it were closed, the detour would be 100 mi (161 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Superstructure | 4 Poor | Advanced section loss, deterioration, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Boundary Line Rd. over Whitney Brook built?
It was built in 1929, making it 96 years old in 2025.
What condition is Boundary Line Rd. over Whitney Brook in?
The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in June 2024.
How much traffic does Boundary Line Rd. over Whitney Brook carry?
About 153 vehicles per day (2016 count), of which roughly 5% are trucks.
How long is Boundary Line Rd. over Whitney Brook?
The structure is 24 ft (7.3 m) long with a longest span of 20 ft (6.1 m) and a deck 27 ft wide.
Who owns Boundary Line Rd. over Whitney Brook?
It is owned by the State Highway Agency.