S Main ST over Little Androscoggin Riv
GoodAndroscoggin County, Maine · 0.3 MI S of JCT RTE 121 · Structure no. 5009
- Built
- 1998
- 27 years old
- Condition
- Good
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 179 ft
- 2 main spans
- Daily traffic
- 4,004
- 2016 count
- Owner
- State
- State Highway Agency
About this bridge
S Main ST over Little Androscoggin Riv is a steel continuous stringer/multi-beam or girder carrying S Main ST over Little Androscoggin Riv in Androscoggin County, Maine. It was built in 1998, so it is 27 years old, younger than the Maine average of 53.7 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 4,004 vehicles a day, roughly 5% of them trucks, projected to reach 5,606 by 2036. The structure is 179 ft (54.6 m) long and 36 ft wide. If it were closed, the detour would be 6.8 mi (11 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was S Main ST over Little Androscoggin Riv built?
It was built in 1998, making it 27 years old in 2025.
What condition is S Main ST over Little Androscoggin Riv in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2024.
How much traffic does S Main ST over Little Androscoggin Riv carry?
About 4,004 vehicles per day (2016 count), of which roughly 5% are trucks.
How long is S Main ST over Little Androscoggin Riv?
The structure is 179 ft (54.6 m) long with a longest span of 89 ft (27 m) and a deck 36 ft wide.
Who owns S Main ST over Little Androscoggin Riv?
It is owned by the State Highway Agency.