I 290 EB over Comb Lk Quinsig&lk Av N
FairWorcester County, Massachusetts · I-290 Mm 10 · Structure no. S140211RADOTNBI
- Built
- 1968
- 57 years old
- Condition
- Fair
- inspected August 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 845 ft
- 3 main spans
- Daily traffic
- 39,309
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
I 290 EB over Comb Lk Quinsig&lk Av N is a steel continuous stringer/multi-beam or girder carrying I 290 EB over Comb Lk Quinsig&lk Av N in Worcester County, Massachusetts. It was built in 1968, so it is 57 years old, younger than the Massachusetts average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 6 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 39,309 vehicles a day, roughly 9% of them trucks, projected to reach 66,331 by 2031. The structure is 845 ft (257.6 m) long and 56 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 6 Satisfactory | Structural elements show some minor deterioration. |
| Superstructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was I 290 EB over Comb Lk Quinsig&lk Av N built?
It was built in 1968, making it 57 years old in 2025.
What condition is I 290 EB over Comb Lk Quinsig&lk Av N in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in August 2024.
How much traffic does I 290 EB over Comb Lk Quinsig&lk Av N carry?
About 39,309 vehicles per day (2023 count), of which roughly 9% are trucks.
How long is I 290 EB over Comb Lk Quinsig&lk Av N?
The structure is 845 ft (257.6 m) long with a longest span of 342 ft (104.2 m) and a deck 56 ft wide.
Who owns I 290 EB over Comb Lk Quinsig&lk Av N?
It is owned by the State Highway Agency.