US Bridges

New Boston Road over Miller River

GoodPosted for load

Worcester County, Massachusetts · 16.09 KM N of Gardner · Structure no. CEPNEDMA2510014

Built
1900
125 years old, rebuilt 1976
Condition
Good
inspected August 2023
Type
Slab
Prestressed Concrete
Length
41 ft
1 main span
Daily traffic
50
2019 count
Owner
Federal
Corps of Engineers (Civil)

About this bridge

New Boston Road over Miller River is a prestressed concrete slab carrying New Boston Road over Miller River in Worcester County, Massachusetts. It was built in 1900 and reconstructed in 1976, so it is 125 years old, older than the Massachusetts average of 63.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. Its operating status is: posted for load restriction.

It carries about 50 vehicles a day, projected to reach 50 by 2040. The structure is 41 ft (12.6 m) long and 20 ft wide. If it were closed, the detour would be 9.9 mi (16 km).

CarriesNew Boston Road
CrossesMiller River
Location16.09 KM N of Gardner
RouteFederal Lands Road 0
Coordinates42.6456, -72.09873
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionAugust 2023
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourScour critical; foundations unstable for calculated scour conditions
Structural evaluation7: Better than present minimum criteria
Waterway adequacy6: Equal to present minimum criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating48.9 US tons
Inventory rating37.8 US tons

Structure

Structure typeSlab
MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans1
Design loadH 15
Structure length41 ft (12.6 m)
Longest span40 ft (12.1 m)
Deck width20 ft (6 m)
Roadway width18 ft (5.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic50 (2019)
Projected traffic50 by 2040
Trucks—
Lanes on structure2
Traffic directionOne-lane bridge for two-way traffic
CarriesHighway and pedestrian
CrossesWaterway
Detour if closed9.9 mi (16 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCorps of Engineers (Civil)
Maintained byCorps of Engineers (Civil)
Historic statusNot eligible for the National Register of Historic Places
Work proposedOther structural work, including hydraulic replacements
Estimated improvement cost$30,000
NavigationNo navigation control on waterway

Frequently asked questions

When was New Boston Road over Miller River built?

It was built in 1900, making it 125 years old in 2025. It was reconstructed in 1976.

What condition is New Boston Road over Miller River in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.

How much traffic does New Boston Road over Miller River carry?

About 50 vehicles per day (2019 count).

How long is New Boston Road over Miller River?

The structure is 41 ft (12.6 m) long with a longest span of 40 ft (12.1 m) and a deck 20 ft wide.

Who owns New Boston Road over Miller River?

It is owned by the Corps of Engineers (Civil).