US Bridges

I 90 Ramp D over Other Relief

Good

Suffolk County, Massachusetts · I 90 Exit 22 · Structure no. B16301B8FDOTNBI

Built
1981
44 years old
Condition
Good
inspected April 2024
Type
Stringer/Multi-beam or Girder
Steel
Length
111 ft
2 main spans
Daily traffic
19,396
2024 count
Owner
State
State Highway Agency

About this bridge

I 90 Ramp D over Other Relief is a steel stringer/multi-beam or girder carrying I 90 Ramp D over Other Relief in Suffolk County, Massachusetts. It was built in 1981, so it is 44 years old, younger than the Massachusetts average of 63.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 19,396 vehicles a day, roughly 3% of them trucks. The structure is 111 ft (33.8 m) long and 34 ft wide. If it were closed, the detour would be 4.3 mi (7 km).

CarriesI 90 Ramp D
CrossesOther Relief
LocationI 90 Exit 22
RouteInterstate 90
Coordinates42.34691, -71.07872
Functional classUrban Principal Arterial - Interstate

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure8 Very GoodNo problems noted.
Last inspectionApril 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry2: Basically intolerable, requiring high priority of replacement
Approach roadway alignment6: Equal to present minimum criteria
Operating rating67.9 US tons
Inventory rating40.7 US tons

Structure

MaterialSteel
DeckConcrete, cast-in-place
Main spans2
Design loadHS 20
Structure length111 ft (33.8 m)
Longest span58 ft (17.6 m)
Deck width34 ft (10.4 m)
Roadway width30 ft (9.1 m)
Vertical clearance over deck0 ft (0 m)

Traffic and service

Average daily traffic19,396 (2024)
Projected traffic—
Trucks3%
Lanes on structure2
Traffic directionOne-way traffic
CarriesHighway
CrossesOther
Detour if closed4.3 mi (7 km)
TollOn a toll road
National Highway SystemYes

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedReplacement because of substandard load-carrying capacity or roadway geometry
Estimated improvement cost$6.9 million (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was I 90 Ramp D over Other Relief built?

It was built in 1981, making it 44 years old in 2025.

What condition is I 90 Ramp D over Other Relief in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.

How much traffic does I 90 Ramp D over Other Relief carry?

About 19,396 vehicles per day (2024 count), of which roughly 3% are trucks.

How long is I 90 Ramp D over Other Relief?

The structure is 111 ft (33.8 m) long with a longest span of 58 ft (17.6 m) and a deck 34 ft wide.

Who owns I 90 Ramp D over Other Relief?

It is owned by the State Highway Agency.