ST105 Front ST over I 195
FairPlymouth County, Massachusetts · .7 MI N of US 6 · Structure no. M0500647XDOTNBI
- Built
- 1971
- 54 years old
- Condition
- Fair
- inspected November 2024
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 235 ft
- 2 main spans
- Daily traffic
- 5,971
- 2024 count
- Owner
- State
- State Highway Agency
About this bridge
ST105 Front ST over I 195 is a steel continuous stringer/multi-beam or girder carrying ST105 Front ST over I 195 in Plymouth County, Massachusetts. It was built in 1971, so it is 54 years old, younger than the Massachusetts average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
It carries about 5,971 vehicles a day, roughly 13% of them trucks, projected to reach 18,952 by 2031. The structure is 235 ft (71.6 m) long and 98 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was ST105 Front ST over I 195 built?
It was built in 1971, making it 54 years old in 2025.
What condition is ST105 Front ST over I 195 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in November 2024.
How much traffic does ST105 Front ST over I 195 carry?
About 5,971 vehicles per day (2024 count), of which roughly 13% are trucks.
How long is ST105 Front ST over I 195?
The structure is 235 ft (71.6 m) long with a longest span of 114 ft (34.7 m) and a deck 98 ft wide.
Who owns ST105 Front ST over I 195?
It is owned by the State Highway Agency.