ST 3 Ramp Xx over HWY Centre ST
GoodNorfolk County, Massachusetts · Quincy Adams Station · Structure no. Q010519PNDOTNBI
- Built
- 2009
- 16 years old
- Condition
- Good
- inspected September 2023
- Type
- Stringer/Multi-beam or Girder
- Steel Continuous
- Length
- 804 ft
- 8 main spans
- Daily traffic
- 27,770
- 2023 count
- Owner
- State
- State Highway Agency
About this bridge
ST 3 Ramp Xx over HWY Centre ST is a steel continuous stringer/multi-beam or girder carrying ST 3 Ramp Xx over HWY Centre ST in Norfolk County, Massachusetts. It was built in 2009, so it is 16 years old, younger than the Massachusetts average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 27,770 vehicles a day, roughly 7% of them trucks, projected to reach 28,427 by 2032. The structure is 804 ft (245 m) long and 33 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was ST 3 Ramp Xx over HWY Centre ST built?
It was built in 2009, making it 16 years old in 2025.
What condition is ST 3 Ramp Xx over HWY Centre ST in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2023.
How much traffic does ST 3 Ramp Xx over HWY Centre ST carry?
About 27,770 vehicles per day (2023 count), of which roughly 7% are trucks.
How long is ST 3 Ramp Xx over HWY Centre ST?
The structure is 804 ft (245 m) long with a longest span of 145 ft (44.2 m) and a deck 33 ft wide.
Who owns ST 3 Ramp Xx over HWY Centre ST?
It is owned by the State Highway Agency.