US Bridges

ST114 A/Fall River over I 195

Good

Bristol County, Massachusetts · 0.5 MI SE R.I. Sl · Structure no. S08011B65DOTNBI

Built
2012
13 years old
Condition
Good
inspected August 2023
Type
Stringer/Multi-beam or Girder
Steel Continuous
Length
304 ft
2 main spans
Daily traffic
41,500
2023 count
Owner
State
State Highway Agency

About this bridge

ST114 A/Fall River over I 195 is a steel continuous stringer/multi-beam or girder carrying ST114 A/Fall River over I 195 in Bristol County, Massachusetts. It was built in 2012, so it is 13 years old, younger than the Massachusetts average of 63.8 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 41,500 vehicles a day, roughly 6% of them trucks, projected to reach 31,270 by 2032. The structure is 304 ft (92.8 m) long and 78 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesST114 A/Fall River
CrossesI 195
Location0.5 MI SE R.I. Sl
RouteState Highway 114A
Coordinates41.80216, -71.33021
Functional classUrban Minor Arterial

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Last inspectionAugust 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourBridge not over waterway
Structural evaluation7: Better than present minimum criteria
Deck geometry7: Better than present minimum criteria
Approach roadway alignment7: Better than present minimum criteria
Operating rating53.6 US tons
Inventory rating42.9 US tons

Structure

MaterialSteel Continuous
DeckConcrete, cast-in-place
Main spans2
Design loadHL 93
Structure length304 ft (92.8 m)
Longest span150 ft (45.7 m)
Deck width78 ft (23.7 m)
Roadway width64 ft (19.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic41,500 (2023)
Projected traffic31,270 by 2032
Trucks6%
Lanes on structure4
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesHighway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedWidening of existing bridge without deck rehabilitation
Estimated improvement cost$5.6 million (2025 estimate)
NavigationNot applicable (no waterway)

Frequently asked questions

When was ST114 A/Fall River over I 195 built?

It was built in 2012, making it 13 years old in 2025.

What condition is ST114 A/Fall River over I 195 in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.

How much traffic does ST114 A/Fall River over I 195 carry?

About 41,500 vehicles per day (2023 count), of which roughly 6% are trucks.

How long is ST114 A/Fall River over I 195?

The structure is 304 ft (92.8 m) long with a longest span of 150 ft (45.7 m) and a deck 78 ft wide.

Who owns ST114 A/Fall River over I 195?

It is owned by the State Highway Agency.