HWY Slocum ST over Water Acushnet River
GoodBristol County, Massachusetts · 200 Ft E of Riv RD N Bedf · Structure no. A03001AVMMUNNBI
- Built
- 2002
- 23 years old
- Condition
- Good
- inspected August 2023
- Type
- Slab
- Prestressed Concrete
- Length
- 196 ft
- 3 main spans
- Daily traffic
- 6,846
- 2022 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
HWY Slocum ST over Water Acushnet River is a prestressed concrete slab carrying HWY Slocum ST over Water Acushnet River in Bristol County, Massachusetts. It was built in 2002, so it is 23 years old, younger than the Massachusetts average of 63.8 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 6,846 vehicles a day, roughly 6% of them trucks, projected to reach 18,952 by 2032. The structure is 196 ft (59.8 m) long and 53 ft wide. If it were closed, the detour would be 0.6 mi (1 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 7 Good | Some minor problems. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was HWY Slocum ST over Water Acushnet River built?
It was built in 2002, making it 23 years old in 2025.
What condition is HWY Slocum ST over Water Acushnet River in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does HWY Slocum ST over Water Acushnet River carry?
About 6,846 vehicles per day (2022 count), of which roughly 6% are trucks.
How long is HWY Slocum ST over Water Acushnet River?
The structure is 196 ft (59.8 m) long with a longest span of 66 ft (20 m) and a deck 53 ft wide.
Who owns HWY Slocum ST over Water Acushnet River?
It is owned by the Town or Township Highway Agency.