Pioneer RD over Edmondson Creek

Good

Sabine Parish, Louisiana · 1.2 MI S of LA 6 · Structure no. 084300000080655

Built
2016
9 years old
Condition
Good
inspected February 2023
Type
Slab
Concrete
Length
60 ft
3 main spans
Daily traffic
100
2022 count
Owner
County
County Highway Agency

About this bridge

Pioneer RD over Edmondson Creek is a concrete slab carrying Pioneer RD over Edmondson Creek in Sabine Parish, Louisiana. It was built in 2016, so it is 9 years old, younger than the Louisiana average of 43 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 100 vehicles a day, projected to reach 110 by 2042. The structure is 60 ft (18.3 m) long and 27 ft wide. If it were closed, the detour would be 5 mi (8 km).

CarriesPioneer RD
CrossesEdmondson Creek
Location1.2 MI S of LA 6
RouteCounty Highway 0
Coordinates31.53015, -93.52467
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionFebruary 2023
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy7: Better than present minimum criteria
Approach roadway alignment6: Equal to present minimum criteria
Operating rating64.6 US tons
Inventory rating49.6 US tons

Structure

Structure typeSlab
MaterialConcrete
DeckConcrete, precast panels
Main spans3
Design loadHL 93
Structure length60 ft (18.3 m)
Longest span20 ft (6.1 m)
Deck width27 ft (8.2 m)
Roadway width24 ft (7.2 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic100 (2022)
Projected traffic110 by 2042
Trucks—
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed5 mi (8 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was Pioneer RD over Edmondson Creek built?

It was built in 2016, making it 9 years old in 2025.

What condition is Pioneer RD over Edmondson Creek in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in February 2023.

How much traffic does Pioneer RD over Edmondson Creek carry?

About 100 vehicles per day (2022 count).

How long is Pioneer RD over Edmondson Creek?

The structure is 60 ft (18.3 m) long with a longest span of 20 ft (6.1 m) and a deck 27 ft wide.

Who owns Pioneer RD over Edmondson Creek?

It is owned by the County Highway Agency.