LA3265 over Bayou Clear

Good

Rapides Parish, Louisiana · 0.25 Mi. East of US 165 · Structure no. 084008404500251

Built
2005
20 years old
Condition
Good
inspected July 2024
Type
Slab
Concrete
Length
217 ft
11 main spans
Daily traffic
4,368
2021 count
Owner
State
State Highway Agency

About this bridge

LA3265 over Bayou Clear is a concrete slab carrying LA3265 over Bayou Clear in Rapides Parish, Louisiana. It was built in 2005, so it is 20 years old, younger than the Louisiana average of 43 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 4,368 vehicles a day, roughly 14% of them trucks, projected to reach 4,804 by 2041. The structure is 217 ft (66.1 m) long and 53 ft wide. If it were closed, the detour would be 8.7 mi (14 km).

CarriesLA3265
CrossesBayou Clear
Location0.25 Mi. East of US 165
RouteState Highway 3265
Coordinates31.1462, -92.4932
Functional classRural Major Collector

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure7 GoodSome minor problems.
Substructure7 GoodSome minor problems.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionJuly 2024
Inspection intervalevery 24 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation7: Better than present minimum criteria
Deck geometry4: Meets minimum tolerable limits to be left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating51.8 US tons
Inventory rating40 US tons

Structure

Structure typeSlab
MaterialConcrete
DeckConcrete, cast-in-place
Main spans11
Design loadHS 20
Structure length217 ft (66.1 m)
Longest span20 ft (6.1 m)
Deck width53 ft (16.2 m)
Roadway width41 ft (12.5 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic4,368 (2021)
Projected traffic4,804 by 2041
Trucks14%
Lanes on structure3
Traffic directionTwo-way traffic
CarriesHighway and pedestrian
CrossesWaterway
Detour if closed8.7 mi (14 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerState Highway Agency
Maintained byState Highway Agency
Historic statusHistorical significance not determinable at this time
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was LA3265 over Bayou Clear built?

It was built in 2005, making it 20 years old in 2025.

What condition is LA3265 over Bayou Clear in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in July 2024.

How much traffic does LA3265 over Bayou Clear carry?

About 4,368 vehicles per day (2021 count), of which roughly 14% are trucks.

How long is LA3265 over Bayou Clear?

The structure is 217 ft (66.1 m) long with a longest span of 20 ft (6.1 m) and a deck 53 ft wide.

Who owns LA3265 over Bayou Clear?

It is owned by the State Highway Agency.