GoodParke County, Indiana · 00.30 N of Jessup RD · Structure no. 6100039
- Built
- 1991
- 34 years old
- Condition
- Good
- inspected April 2024
- Type
- Stringer/Multi-beam or Girder
- Prestressed Concrete Continuous
- Length
- 172 ft
- 3 main spans
- Daily traffic
- 64
- 2018 count
- Owner
- County
- County Highway Agency
About this bridge
Pipeline RD over Little Raccoon Creek is a prestressed concrete continuous stringer/multi-beam or girder carrying Pipeline RD over Little Raccoon Creek in Parke County, Indiana. It was built in 1991, so it is 34 years old, younger than the Indiana average of 46.6 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 64 vehicles a day, roughly 4% of them trucks, projected to reach 76 by 2038. The structure is 172 ft (52.4 m) long and 27 ft wide. If it were closed, the detour would be 2.5 mi (4 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 8 Very Good | No problems noted. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Pipeline RD over Little Raccoon Creek built?
It was built in 1991, making it 34 years old in 2025.
What condition is Pipeline RD over Little Raccoon Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in April 2024.
How much traffic does Pipeline RD over Little Raccoon Creek carry?
About 64 vehicles per day (2018 count), of which roughly 4% are trucks.
How long is Pipeline RD over Little Raccoon Creek?
The structure is 172 ft (52.4 m) long with a longest span of 57 ft (17.4 m) and a deck 27 ft wide.
Who owns Pipeline RD over Little Raccoon Creek?
It is owned by the County Highway Agency.