CR 850E over Tail Run
GoodHenry County, Indiana · 00.35 N of CR 300 S · Structure no. 3300204
- Built
- 1975
- 50 years old, rebuilt 2022
- Condition
- Good
- inspected August 2023
- Type
- Stringer/Multi-beam or Girder
- Steel
- Length
- 50 ft
- 1 main span
- Daily traffic
- 100
- 2019 count
- Owner
- County
- County Highway Agency
About this bridge
CR 850E over Tail Run is a steel stringer/multi-beam or girder carrying CR 850E over Tail Run in Henry County, Indiana. It was built in 1975 and reconstructed in 2022, so it is 50 years old, older than the Indiana average of 46.6 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 100 vehicles a day, roughly 5% of them trucks, projected to reach 150 by 2037. The structure is 50 ft (15.2 m) long and 25 ft wide. If it were closed, the detour would be 1.9 mi (3 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 8 Very Good | No problems noted. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 8 Very Good | No problems noted. |
| Channel and channel protection | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was CR 850E over Tail Run built?
It was built in 1975, making it 50 years old in 2025. It was reconstructed in 2022.
What condition is CR 850E over Tail Run in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in August 2023.
How much traffic does CR 850E over Tail Run carry?
About 100 vehicles per day (2019 count), of which roughly 5% are trucks.
How long is CR 850E over Tail Run?
The structure is 50 ft (15.2 m) long with a longest span of 49 ft (14.9 m) and a deck 25 ft wide.
Who owns CR 850E over Tail Run?
It is owned by the County Highway Agency.