TR 87 a over Trib N Br. Crow CR

Good

Marshall County, Illinois · Sec 1 T29N R1W · Structure no. 062476700000000

Built
2015
10 years old
Condition
Good
inspected September 2021
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
70 ft
1 main span
Daily traffic
50
2024 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

TR 87 a over Trib N Br. Crow CR is a prestressed concrete box beam or girders - multiple carrying TR 87 a over Trib N Br. Crow CR in Marshall County, Illinois. It was built in 2015, so it is 10 years old, younger than the Illinois average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 50 vehicles a day, roughly 40% of them trucks, projected to reach 51 by 2046. The structure is 70 ft (21.2 m) long and 24 ft wide.

CarriesTR 87 a
CrossesTrib N Br. Crow CR
LocationSec 1 T29N R1W
RouteCounty Highway 0
Coordinates41.00018, -89.17434
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Channel and channel protection7 GoodSome minor problems.
Last inspectionSeptember 2021
Inspection intervalevery 48 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation8: Equal to present desirable criteria
Deck geometry6: Equal to present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating46.4 US tons
Inventory rating35.7 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans1
Design loadHS 25 or greater
Structure length70 ft (21.2 m)
Longest span67 ft (20.4 m)
Deck width24 ft (7.3 m)
Roadway width24 ft (7.3 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic50 (2024)
Projected traffic51 by 2046
Trucks40%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesRelief for waterway
Detour if closed—
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was TR 87 a over Trib N Br. Crow CR built?

It was built in 2015, making it 10 years old in 2025.

What condition is TR 87 a over Trib N Br. Crow CR in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in September 2021.

How much traffic does TR 87 a over Trib N Br. Crow CR carry?

About 50 vehicles per day (2024 count), of which roughly 40% are trucks.

How long is TR 87 a over Trib N Br. Crow CR?

The structure is 70 ft (21.2 m) long with a longest span of 67 ft (20.4 m) and a deck 24 ft wide.

Who owns TR 87 a over Trib N Br. Crow CR?

It is owned by the Town or Township Highway Agency.