Michael Rd/Tr 305A over Sugar Ck
GoodMadison County, Illinois · 1.5MI E Highland · Structure no. 060334600000000
- Built
- 2011
- 14 years old
- Condition
- Good
- inspected November 2024
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 112 ft
- 3 main spans
- Daily traffic
- 525
- 2021 count
- Owner
- Town / Township
- Town or Township Highway Agency
About this bridge
Michael Rd/Tr 305A over Sugar Ck is a prestressed concrete box beam or girders - multiple carrying Michael Rd/Tr 305A over Sugar Ck in Madison County, Illinois. It was built in 2011, so it is 14 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 525 vehicles a day, roughly 11% of them trucks, projected to reach 562 by 2046. The structure is 112 ft (34.1 m) long and 30 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Michael Rd/Tr 305A over Sugar Ck built?
It was built in 2011, making it 14 years old in 2025.
What condition is Michael Rd/Tr 305A over Sugar Ck in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in November 2024.
How much traffic does Michael Rd/Tr 305A over Sugar Ck carry?
About 525 vehicles per day (2021 count), of which roughly 11% are trucks.
How long is Michael Rd/Tr 305A over Sugar Ck?
The structure is 112 ft (34.1 m) long with a longest span of 50 ft (15.2 m) and a deck 30 ft wide.
Who owns Michael Rd/Tr 305A over Sugar Ck?
It is owned by the Town or Township Highway Agency.