GoodMacon County, Illinois · 3 MI NW of Macon · Structure no. 058339700000000
- Built
- 2016
- 9 years old
- Condition
- Good
- inspected December 2021
- Type
- Box Beam or Girders - Multiple
- Prestressed Concrete
- Length
- 59 ft
- 1 main span
- Daily traffic
- 100
- 2020 count
- Owner
- County
- County Highway Agency
About this bridge
Ch 29 (boody Rd) over Mosquito Creek is a prestressed concrete box beam or girders - multiple carrying Ch 29 (boody Rd) over Mosquito Creek in Macon County, Illinois. It was built in 2016, so it is 9 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 7 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 100 vehicles a day, roughly 12% of them trucks, projected to reach 101 by 2046. The structure is 59 ft (18 m) long and 27 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 7 Good | Some minor problems. |
| Superstructure | 7 Good | Some minor problems. |
| Substructure | 7 Good | Some minor problems. |
| Channel and channel protection | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Ch 29 (boody Rd) over Mosquito Creek built?
It was built in 2016, making it 9 years old in 2025.
What condition is Ch 29 (boody Rd) over Mosquito Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in December 2021.
How much traffic does Ch 29 (boody Rd) over Mosquito Creek carry?
About 100 vehicles per day (2020 count), of which roughly 12% are trucks.
How long is Ch 29 (boody Rd) over Mosquito Creek?
The structure is 59 ft (18 m) long with a longest span of 56 ft (17.2 m) and a deck 27 ft wide.
Who owns Ch 29 (boody Rd) over Mosquito Creek?
It is owned by the County Highway Agency.