Rakow RD (ch V-29) over Crystal Creek
GoodMcHenry County, Illinois · 0.24 Mi. N of Ackman · Structure no. 056315700000000
- Built
- 1994
- 31 years old, rebuilt 2010
- Condition
- Good
- inspected October 2022
- Type
- Culvert
- Concrete
- Length
- 23 ft
- 2 main spans
- Daily traffic
- 30,600
- 2021 count
- Owner
- County
- County Highway Agency
About this bridge
Rakow RD (ch V-29) over Crystal Creek is a concrete culvert carrying Rakow RD (ch V-29) over Crystal Creek in McHenry County, Illinois. It was built in 1994 and reconstructed in 2010, so it is 31 years old, younger than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
It carries about 30,600 vehicles a day, roughly 4% of them trucks, projected to reach 18,360 by 2046. The structure is 23 ft (7.1 m) long and 112 ft wide.
Location
Open in Google MapsCondition and inspection
All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.
| Component | Rating | Meaning |
|---|---|---|
| Channel and channel protection | 7 Good | Some minor problems. |
| Culvert | 8 Very Good | No problems noted. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Rakow RD (ch V-29) over Crystal Creek built?
It was built in 1994, making it 31 years old in 2025. It was reconstructed in 2010.
What condition is Rakow RD (ch V-29) over Crystal Creek in?
The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in October 2022.
How much traffic does Rakow RD (ch V-29) over Crystal Creek carry?
About 30,600 vehicles per day (2021 count), of which roughly 4% are trucks.
How long is Rakow RD (ch V-29) over Crystal Creek?
The structure is 23 ft (7.1 m) long with a longest span of 11 ft (3.4 m) and a deck 112 ft wide.
Who owns Rakow RD (ch V-29) over Crystal Creek?
It is owned by the County Highway Agency.