US Bridges

CH-27 (johnson Rd) over Nippersink CR

PoorPosted for load

McHenry County, Illinois · 0.6 M NE Durkee RD · Structure no. 056312800000000

Built
1978
47 years old
Condition
Poor
inspected September 2024
Type
Box Beam or Girders - Multiple
Prestressed Concrete
Length
97 ft
2 main spans
Daily traffic
300
2021 count
Owner
County
County Highway Agency

About this bridge

CH-27 (johnson Rd) over Nippersink CR is a prestressed concrete box beam or girders - multiple carrying CH-27 (johnson Rd) over Nippersink CR in McHenry County, Illinois. It was built in 1978, so it is 47 years old, older than the Illinois average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in poor condition with a lowest component rating of 3 out of 9. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. Its operating status is: posted for load restriction.

It carries about 300 vehicles a day, roughly 9% of them trucks, projected to reach 360 by 2046. The structure is 97 ft (29.7 m) long and 26 ft wide.

CarriesCH-27 (johnson Rd)
CrossesNippersink CR
Location0.6 M NE Durkee RD
RouteCounty Highway 0
Coordinates42.43643, -88.45818
Functional classRural Local

Condition and inspection

Poor

The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions.

ComponentRatingMeaning
Deck7 GoodSome minor problems.
Superstructure3 SeriousLoss of section, deterioration, spalling or scour have seriously affected primary structural components.
Substructure6 SatisfactoryStructural elements show some minor deterioration.
Channel and channel protection7 GoodSome minor problems.
Last inspectionSeptember 2024
Inspection intervalevery 24 months
Operating statusPosted for load restriction
ScourFoundations stable; scour above top of footing
Structural evaluation3: Basically intolerable, requiring high priority of corrective action
Deck geometry5: Somewhat better than minimum adequacy to tolerate being left in place as is
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating20 US tons
Inventory rating11.8 US tons

Structure

MaterialPrestressed Concrete
DeckConcrete, precast panels
Main spans2
Design loadHS 20
Structure length97 ft (29.7 m)
Longest span47 ft (14.3 m)
Deck width26 ft (7.9 m)
Roadway width26 ft (7.9 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic300 (2021)
Projected traffic360 by 2046
Trucks9%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed—
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerCounty Highway Agency
Maintained byCounty Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was CH-27 (johnson Rd) over Nippersink CR built?

It was built in 1978, making it 47 years old in 2025.

What condition is CH-27 (johnson Rd) over Nippersink CR in?

The National Bridge Inventory rates it in poor condition. The lowest-rated primary component is rated 4 or below, indicating advanced deterioration. Poor does not mean unsafe; such bridges are inspected more often and may carry load restrictions. The last reported inspection was in September 2024.

How much traffic does CH-27 (johnson Rd) over Nippersink CR carry?

About 300 vehicles per day (2021 count), of which roughly 9% are trucks.

How long is CH-27 (johnson Rd) over Nippersink CR?

The structure is 97 ft (29.7 m) long with a longest span of 47 ft (14.3 m) and a deck 26 ft wide.

Who owns CH-27 (johnson Rd) over Nippersink CR?

It is owned by the County Highway Agency.