US Bridges

TR 155 over Drainage Ditch

Good

Livingston County, Illinois · 3420 E 1450 N · Structure no. 053407300000000

Built
1983
42 years old
Condition
Good
inspected June 2022
Type
Channel Beam
Concrete
Length
68 ft
3 main spans
Daily traffic
25
2023 count
Owner
Town / Township
Town or Township Highway Agency

About this bridge

TR 155 over Drainage Ditch is a concrete channel beam carrying TR 155 over Drainage Ditch in Livingston County, Illinois. It was built in 1983, so it is 42 years old, younger than the Illinois average of 45.3 years.

The most recent inspection reported to the Federal Highway Administration rates it in good condition with a lowest component rating of 8 out of 9. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

It carries about 25 vehicles a day, projected to reach 25 by 2046. The structure is 68 ft (20.7 m) long and 26 ft wide. If it were closed, the detour would be 3.7 mi (6 km).

CarriesTR 155
CrossesDrainage Ditch
Location3420 E 1450 N
RouteCounty Highway 0
Coordinates40.84146, -88.27688
Functional classRural Local

Condition and inspection

Good

All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted.

ComponentRatingMeaning
Deck8 Very GoodNo problems noted.
Superstructure8 Very GoodNo problems noted.
Substructure8 Very GoodNo problems noted.
Channel and channel protection6 SatisfactoryStructural elements show some minor deterioration.
Last inspectionJune 2022
Inspection intervalevery 48 months
Operating statusOpen, no restriction
ScourFoundations stable; scour above top of footing
Structural evaluation8: Equal to present desirable criteria
Deck geometry6: Equal to present minimum criteria
Waterway adequacy8: Equal to present desirable criteria
Approach roadway alignment8: Equal to present desirable criteria
Operating rating48.9 US tons
Inventory rating35.7 US tons

Structure

Structure typeChannel Beam
MaterialConcrete
DeckConcrete, precast panels
Main spans3
Design loadHS 20
Structure length68 ft (20.7 m)
Longest span22 ft (6.7 m)
Deck width26 ft (8 m)
Roadway width26 ft (7.8 m)
Vertical clearance over deckUnrestricted

Traffic and service

Average daily traffic25 (2023)
Projected traffic25 by 2046
Trucks0%
Lanes on structure2
Traffic directionTwo-way traffic
CarriesHighway
CrossesWaterway
Detour if closed3.7 mi (6 km)
TollOn a free road
National Highway SystemNo

Ownership and planned work

OwnerTown or Township Highway Agency
Maintained byTown or Township Highway Agency
Historic statusNot eligible for the National Register of Historic Places
Work proposedNone recorded
Estimated improvement cost—
NavigationNo navigation control on waterway

Frequently asked questions

When was TR 155 over Drainage Ditch built?

It was built in 1983, making it 42 years old in 2025.

What condition is TR 155 over Drainage Ditch in?

The National Bridge Inventory rates it in good condition. All primary components (deck, superstructure, substructure, or culvert) are rated 7 or higher. No significant problems were noted. The last reported inspection was in June 2022.

How much traffic does TR 155 over Drainage Ditch carry?

About 25 vehicles per day (2023 count).

How long is TR 155 over Drainage Ditch?

The structure is 68 ft (20.7 m) long with a longest span of 22 ft (6.7 m) and a deck 26 ft wide.

Who owns TR 155 over Drainage Ditch?

It is owned by the Town or Township Highway Agency.