Peplow Road over Virgil DR Ditch NO.3
FairPosted for loadKane County, Illinois · 0.5 MI W Virgil · Structure no. 045300200000000
- Built
- 1929
- 96 years old
- Condition
- Fair
- inspected April 2023
- Type
- Slab
- Concrete
- Length
- 26 ft
- 1 main span
- Daily traffic
- 600
- 2023 count
- Owner
- County
- County Highway Agency
About this bridge
Peplow Road over Virgil DR Ditch NO.3 is a concrete slab carrying Peplow Road over Virgil DR Ditch NO.3 in Kane County, Illinois. It was built in 1929, so it is 96 years old, older than the Illinois average of 45.3 years.
The most recent inspection reported to the Federal Highway Administration rates it in fair condition with a lowest component rating of 5 out of 9. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. Its operating status is: posted for load restriction.
It carries about 600 vehicles a day, roughly 18% of them trucks, projected to reach 915 by 2046. The structure is 26 ft (7.9 m) long and 26 ft wide. If it were closed, the detour would be 3.7 mi (6 km).
Location
Open in Google MapsCondition and inspection
The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound.
| Component | Rating | Meaning |
|---|---|---|
| Deck | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Superstructure | 5 Fair | All primary structural elements are sound but may have minor section loss, cracking, spalling or scour. |
| Substructure | 6 Satisfactory | Structural elements show some minor deterioration. |
| Channel and channel protection | 6 Satisfactory | Structural elements show some minor deterioration. |
Structure
Traffic and service
Ownership and planned work
Frequently asked questions
When was Peplow Road over Virgil DR Ditch NO.3 built?
It was built in 1929, making it 96 years old in 2025.
What condition is Peplow Road over Virgil DR Ditch NO.3 in?
The National Bridge Inventory rates it in fair condition. The lowest-rated primary component is rated 5 or 6. Minor deterioration is present but the structure is sound. The last reported inspection was in April 2023.
How much traffic does Peplow Road over Virgil DR Ditch NO.3 carry?
About 600 vehicles per day (2023 count), of which roughly 18% are trucks.
How long is Peplow Road over Virgil DR Ditch NO.3?
The structure is 26 ft (7.9 m) long with a longest span of 25 ft (7.6 m) and a deck 26 ft wide.
Who owns Peplow Road over Virgil DR Ditch NO.3?
It is owned by the County Highway Agency.